Manson Project Update: March 21, 2001
On the afternoon of March 19, 2001, a City of Toronto building inspector
noted that demolition activities around the hopper at the north end of the
factory building were in progress at the site. The City immediately notified
the MOE, MOL, Candec Consultants and the Peer reviewer.
Subsequently, Allison Lee Lai of the MOE visited the site and issued a
written Order to Comply requiring that the four stationary hi-vol monitors
be reinstalled until the project is completed. The contractor ordered that
all activities be suspended immediately to comply with this order.
MOL inspector and an Engineer from the Peer Reviewer also visited the site
in the afternoon. The contractor, MOL inspector and Peer Reviewer's
inspector were of the opinion that the remaining portion of the hopper was
in an unsafe condition and should be taken down prior to shutting down the
demolition activities.
With the concurrence of the Building Division, the demolition of the
remainder of the hopper was completed in approximately 10 minutes towards
the end of the day in the presence of MOL and the Peer Reviewer. Peer
reviewer reports that during this work, water was continuously used to
control dust, a roving hi-vol monitor was placed downwind of the work and
only minor lime dust was generated.
An update from Candec Consultants per City's request of March 19, 2001 is
expected shortly.
|